Hi
the SAT & FAT must written in IQ protocol or each of them must have a unique protocol?
best regards


(Md.Asif Hussain) #2

Better to have separate oneā€¦

Thanks


(Albert Groeneveld) #3

FAT document should be separate from SAT.
SAT can be based on FAT with additional information/tests
SAT can be split in to OQ and IQ


(Nguyen hoai giang vu) #4

FAT should be performed in advance before delivering the machine to the customer site. Then the SAT will be peformed. The IQ included FAT and SAT . You can take the result from SAT to be a part of the OQ