Change control required for new sop

(Manoj Singh) #1

Is change control required for preparation of new sop

(Ankur Choudhary) #2

No, change control is not required to prepare new SOP but it is required to change the existing SOP.

2 Likes
(pradeep_pharma01) #3

No ,CC is required for each and every thing either new or change

1 Like
(Potla Narasimha Rao) #4

I think it is wrong. for introduction,addition,deletion and for modification of existing facility document should be addressed through change request.

1 Like
(dushyant) #5

Any modification/addition/deletion in existing system for betterment purpose we need to raise CCN. However any introduction system can also introduced through CCN.