Change control handling and closing

How can we close change control taken for 3 validation API and reprocess batches, if 1 or 2 batches manufacturing is not under planning?

Based on manufactured batches data,interim summary report can be approved and based on this CCF can be closed with justification as
“no more plan of said batches in future.
New CCF will be raised in future for such requirement of validation.”

1 Like

Thank u…may I know what about closure of those validation batch specially reprocess batch…is it possible to close them on basis of interim report or we should wait for batches for final report.